Re-plan an active assignment
Re-plan from Timeline when an Active milestone needs more or less time. Rectangle proposes the complete downstream cascade first; it does not silently move the schedule as soon as you drag or choose a date.
Choose the boundary to change
Section titled “Choose the boundary to change”Drag a milestone edge on the calendar, or select Adjust on the milestone when direct date entry is easier.
- Choose the milestone.
- Set its New end date.
- Select Review changes.
Cancel if you opened the wrong milestone. No plan changes are applied at this step.
Review the cascade
Section titled “Review the cascade”The Re-plan review names how the changed milestone and every later milestone will move. Check for:
- ordinary downstream shifts;
- pinned dates that must hold;
- gaps created before a pinned milestone;
- overlaps or other conflicts that need correction.
Select Apply new plan only when the complete result is right. Cancel returns to the unchanged schedule.
If the plan cannot be applied
Section titled “If the plan cannot be applied”Release a pin that no longer represents a real constraint, or choose a boundary that does not create an invalid overlap. If Rectangle reports a stale change from another tab, refresh the assignment, review the current schedule, and propose the change again.
Re-planning changes dates, not student submission history. Use Project when milestone content needs to change.