Edit the project for one assignment
Use assignment editing when one class needs a tailored version of a project. You work in the familiar authoring workspace, but every saved change belongs to this assignment only. The reusable project in Find or Library—and assignments created for other classes—stay unchanged.
Open the assignment copy
Section titled “Open the assignment copy”From the assignment, open Actions and select Edit Assignment. Draft and Staged assignments also provide two direct doorways from Project:
- Select Edit in authoring for the whole copy.
- Select Edit rubric to open directly to the rubric editor.
The location trail begins with Assign, names the assignment, and ends at Edit assignment. The notice below the tabs confirms that the project identity comes from the template while the template stays untouched. Select Edit the template instead only when the reusable project itself should change.
The five tabs in this workspace belong to the assignment copy:
- Project gives you the whole-project view. The title, driving question, subjects, grades, duration, student brief, product, and audience remain inherited from the template.
- Milestones edits the content students encounter inside each stage.
- Rubric edits the assignment’s criteria and performance levels.
- Reading View proofs the assembled teacher or student document.
- Review compares this assignment with its source template.
Edit milestones and deliverables
Section titled “Edit milestones and deliverables”In Milestones, select a milestone from the left rail. You can:
- edit its title and description;
- add or remove content standards while the assignment is still a Draft;
- edit a deliverable’s title, description, submission mode, and submission format;
- add another deliverable.
The duration is labeled as of load and cannot be changed here. Use the assignment’s Schedule tab for timing. Assignment editing also does not add, remove, or reorder milestones, or remove and reorder existing deliverables. Those boundaries prevent a content edit from silently changing the class schedule or disconnecting submitted work.
Edit the assignment rubric
Section titled “Edit the assignment rubric”In Rubric, select a criterion to edit its name, weight, and four observable performance levels. You can also add a criterion.
For a Draft assignment, saved criteria can have practice and habit standards attached. If you add a new criterion, select Save changes first so Rectangle can create its assignment record; then attach standards. Existing criteria cannot be removed from this workspace because scores or student evidence may already depend on them.
Proof what teachers and students will read
Section titled “Proof what teachers and students will read”Use Reading View to read the complete assignment copy as one document. Switch between Teacher and Student to confirm that the framing, milestones, standards, deliverables, and rubric make sense for the intended audience. Print uses whichever audience is selected.
Review differences from the template
Section titled “Review differences from the template”Review is a read-only comparison between this assignment and its source project. It groups changed milestone and rubric content, shows before-and-after language, and links back to the tab where each item can be edited. The change count remains visible across the workspace.
If the source template changed after this assignment was created, Review says that some comparisons may not line up. It never copies those later template changes into the assignment automatically.
Save before leaving
Section titled “Save before leaving”Assignment editing uses an explicit save because students may already be working from this copy. After your first change, the top navigation changes from All changes saved to Unsaved changes and shows Save changes. Select it, or use Command-S on macOS or Control-S on Windows.
If you try to leave with unsaved work, Rectangle lets you Save & leave, Stay & keep editing, or Leave without saving. When a co-teacher saved a newer version while you were editing, Rectangle asks you to reload their version or overwrite it with yours instead of silently choosing one.
After saving, follow the assignment name in the location trail to return to Assign and review the updated class copy in its operational context.